References of S.W.H. GROUP SE

Since 2006, a team of our company in the Czech Republic has worked on a variety of projects, from the first draft to the overall construction of technological systems, including connections to the network and securing funding. Since 2010, the team expanded abroad, and in the Balkans and then to Poland.

Photovoltaic project 99,20 kW, investor Q PARK Měšice, Czech Republic, installation by S.W.H. GROUP SE - QPARTNER Hanwha Q CELLS


CONSTRUCTION:

  • PVA 2,8 MW, Kopidlno
    part of the overall construction and commissioning in August 2010
    (image)
  • PVA 220 kW, Nové Strašecí
    general engineering, building and put into operation in November 2010
    (image)
  • PVA 2,055 MW, Česká Kamenice
    general engineering, general construction and commissioning in December 2010

    (image, image, image, image)
  • Photovoltaic project 99,20 kW
    investor Q PARK Měšice, Czech Republic, installation by S.W.H. GROUP SE - QPARTNER Hanwha Q CELLS
    (image, image, image, image)
  • Photovoltaic instalation 3,60 kW,
    instalation 9 2018, Pamětice, Czech Republic, by S.W.H. GROUP SE – Panely Hanwha Q CELLS - QPEAK-G4.1 - 300 Wp
    (image, image, image)
  • FVE instalace 3,36 kW,
    instalation říjen 2018, Nové Jirny, Czech Republic, provedl S.W.H. GROUP SE – Panely Hanwha Q CELLS - Q.PLUS BFR-G4.1- 280 Wp
    (imagen, imagen, imagen)

Engineering:

  • PVA 7 MW, U Kyjova
    general engineering 2009 (image)
  • PVA 300 kW, Sazovice
    general engineering 2009 (image, image)
  • PVA 5 MW, Otrokovice
    general engineering 2010 (image)
  • PVA 4 MW, Bělá
    final engineering 2010 (image)
  • PVA 1 MW, Buzitka, Slowakei
    general engineering 2010
    (image)
  • PVA 997,57 kW, Dimitrovgrad, Serbia
    general engineering 2011
    (image, image, image)
  • PVA 3 MW, Ljubuški, Bosnia and Herceg.
    general engineering, 2012 (image, image, image)
  • WKW Mokranje, Serbia
    preparation of the project is still in progress
  • WKW 1,882 MW, Crna Trava, Serbia
    actually installed 1,520 MW - Kaplan and Turgi Trubín, put into operation 10/2013 - part of the overall engineering and auditing (image, image)
  • WKW 1,9 MW, Žagubica, Serbia
    actually installed 1.78 MW Francis turbine 3 into service in 2013 - part of the overall engineering and auditing (image, image, image)
  • WEA 50 MW, Wroclaw, Polsko
    team leader for engineering, ongoing
    (image)
  • WEA 60 MW, Šušara, Serbia
    team member for engineering 2012
    (image, image)
  • WEA 44 MW, Tomislavgrad, Bosnia
    and Hercegowina

    team member for engineering, closed 2012 (image, image)

For more info contast us: info@swhgroup.eu

Our suppliers




Quick Contact

S.W.H. GROUP SE
Pobřežní number 620/3, 186 00 Prague 8 – Karlín
Czech Republic, Czech (+420) 728 327 766

info@swhgroup.eu, www.swhgroup.eu

How NET METERING works?